Day 16 - Electrical walk through - Rough in

Met with electricians to go over placement of outlets and switches and discuss add-ons. We were disappointed that the standard lighting in most rooms is a switch to a wall outlet instead of a ceiling light. In fairness we knew that going in. But we think that shouldn't be an upgrade, rather a standard feature.
We were pleased to find out the smoke alarms are all hard wired (with battery backup) as opposed to battery only.

Rough in was completed in 1 day.











 Great Room can lights visible.


 3 Kitchen can lights visible.






 Hanging with the cool kids, our friends the Salles. Glad you made it down!!