Thursday, May 16, 2013

Day 1 of Framing


What a difference a day makes!

Our 110 days until completion clock has started ticking as of Wednesday the 15th. Quite surprised at what the framers accomplished on just the first day. Sill plate and seal has been installed around the entire block wall. Basement poles, main support beams, floor joists and floor decking is complete. They have also begun building many of the wall sections for my garage. Yes... I said MY garage.
With all of the stress of getting the foundation in (see previous posts), the experience to date has not been very fun or exciting. But today standing on the deck, I admit to feeling excited. It now seems like a real house and not just a mud hole. Special thanks to our field manager for addressing a couple issues that popped up this morning


 Buddy claiming the sun room already. There's going to be a fight between him and the Mrs. soon.








Life is goooood!


 The epic battle of wills begins....
"My sun room." No, Mine. "No, mine", Mine!
















Supplies brought out.

Supplies were delivered  Last Thursday and Friday (9th and 10th) in preparation for framing this week.


Thursday, May 9, 2013

Back Fill Complete!

Today we back filled the house. We are now ready to have the framing process started.

 Prior to back fill we had a couple issues. 1 was with the drain tile improperly installed in a few areas. The masons clearly rushed the job to get in and out. The connection of the tile to my natural drain was completely off the drain pipe which would have definitely created a real problem with drainage and my basement. Working with my field manager got the issue resolved as well as could be done in the areas that were still accessible. Special Thanks to our FM for taking care of that for us.


The 2nd issue was our discovery of an additive to our concrete that we had many discussions about not wanting in ours. I was pretty adamant about it not being put it since it is used during low temperature situations and we waited to dig until the temps were not an issue. It was put in anyways as it accelerates the cure of the concrete. The only purpose it served was to allow the masons to start blocking sooner. It causes corrosion of metal and we had added rebar to our footers because I believe it is not possible to overkill the foundation your house is built on - that's just how I view it. Nothing can be done about it now so we just have to live with it. Working with Wayne homes personnel, they did rebate half the cost of the rebar we had paid extra for. Hopefully we will have no issue. Footers should stay in good shape with all the extra gravel we used today at back fill.


 Garage filled with gravel... lots of it.

 Yes, I'm excited to have a real garage finally!


 Inside garage stairwell wall not back filled completely. No brace is on the side so we need to get further along in the build before topping it off.

 Front porch back filled. You can see wall braces in the background.









 Almost 4 feet high of gravel along the entire back of the house. The property has springs behind the house on the hill. The back was the only real concern as far as extra measures to ensure plenty of water handling. Better safe than sorry!







Thursday, May 2, 2013

Wall finished...Including Sun room!

So our Basement wall was completed yesterday. It's pretty cool to see it done. The masons left a great deal of broken block and fragments thrown into the footer areas that will get back filled after waterproofing. While I certainly appreciate any contribution to filling up the space, I am concerned because neither dirt nor gravel can possibly fill all the cells of the block pieces which I would think will lead to more settlement after the floor is poored. I have put my concerns in an email to my Field Mgr. and the Construction Mgr. Anxious to hear their opinion.
 
 Fragments across front of garage.
 
 Fragements down side of garage.
 
Back section of block debris after I had a "therapy session" with my sledge hammer.
This looks like a much better base than the cubes all piled up! But I'm old and lazy and don't think I should have to sledge the remaining 50 feet of it. We'll see what happens.
 
 Proof of success! Full basement under sunroom! Good work everyone!
 
 It's a boy! Oh... That's just the pipe for the future water connection sticking through the wall.